The railway yard at
Eumungerie went through three major evolutions to grow to its most advanced
state. The last quarter of a century has
brought several subsequent rationalisations to return it to much reduced state.
Its initial layout in
1903 involved a single passing loop provided on the western side of the main
line. The station was provided on the
main line. The initial length of the
yard was 270 yards.
The initial track plan
shows nothing in the way of railway infrastructure, apart from a platform,
small station building and water tank. From
1905 livestock and timber were loaded from a loading bank opposite the
platform.
In October 1912 a
contract was let for the provision of a second siding to act as a crossing
loop. Work associated with this first
expansion major expansion of the precinct involved the re-erection of water
tanks, removal and re-erection of platform and station buildings, provision of
a crossing loop and removal and re-erection of cattle yards.
To facilitate these
improvements on Monday, 16 October 1911 Eumungerie was temporarily closed as a
staff or crossing station. All trains
timetabled to cross or pass at Eumungerie were suspended - No 37, a conditional
goods train from Dubbo to Coonamble was not to run. Similarly, No. 26, a conditional goods train
from Gular to Dubbo was not to run. Nos.
11, 27 and 85, all conditional goods trains from Dubbo to Coonamble, were not
to run on Tuesdays, Thursdays and Saturdays in order to avoid crossing the up
mixed train.
As part of the yard’s trackwork
enhancements a 20 ton cart weighbridge was installed at Eumungerie from 2
December 1911. This facility may have
proved to be inadequate or unsound as it was replaced as early as 1915 with a
similar facility.
The most expensive element
of the expansion of Eumungerie was the construction of a station officer’s
residence, at a cost of ₤686. The second
largest piece of expenditure involved the provision of a larger crossing loop at
a cost of ₤542, including ₤203 worth of railway sleepers.
The removal and
re-erection of the platform and building cost only ₤28 but additions to both
incurred a further ₤128 expenditure.
Other works involving the locomotive water supply cost ₤51 and
cattle-stops ₤44. Ancillary works of ₤14
brought the overall total to ₤1,493.
The rebuilding of the
station building is an interesting matter for consideration. No photographs or descriptions have been
obtained of the original building. The
earliest photographs date from the 1930s and 1940s show glimpses of a typical
NSW Government Railways A3 skillion roof building. As this type of building came into vogue
around 1909 it may be that the original building was not re-erected at all, but
replaced or transferred elsewhere.
Eumungerie yard was reopened
on Monday, 28 October 1912. Seal press
448 was allocated to the station as if to stamp the occasion. However it was not until 1 December 1912 that
Eumungerie station was reopened as a booking office. This event and the completion of the station
officer’s house brought the first full-time rostered railway employee to the
village.
As almost an
afterthought 1913 brought the commissioning of the smaller platform building on
the southern side of the original building.
This construction was described as an ‘out-of’ shed on the official
station register. Its purpose was to
store parcels and small goods making the rail journey into or out of the
village. On Tuesday 8 July 1913 new
signal and interlocking arrangements were also brought into use at Eumungerie.
By the time that all
works were completed in July 1913 a siding had been constructed on the eastern
side of the mainline, which was named subsequently as the Platform Road. The yard had been extended to 594 yards, with
distant signals placed 800 yards from the extremities of the yard.
This first major expansion
of the yard increased the amount of usable track capacity from 324 yards to 932
yards – nearly a three-fold increase over the original yard.
A second expansion of
the railway occurred in 1915 and was associated with the increase in wheat
traffic. A wheat stacking site was
constructed just to the north of where the silos still stand. The same year brought the erection of a 5 ton
gantry crane straddling the siding to the north of the loading bank.
Late in 1915 the siding
was extended at the northern end, creating what became known as a stub-ended
Wheat Siding. Although no NSWGR track
plan has been obtained to show this extension, a 1920 Parish Map clearly shows
this addition. The relevant Weekly
Notices also state that on 23 November 1915 the
siding at Eumungerie was extended at the northern end. The siding could then provide standing room
for 63 four-wheeled trucks.
A further and final expansion
in 1925/26 involved the northward expansion of the Wheat Siding, principally to
provide double-ended access to the wheat silos.
By providing 1,668 yards of usable track capacity the Eumungerie rail
precinct had experienced a five-fold increase in just 25 years.
The 1925/26 track
arrangement represents the maximum expansion of the railway at Eumungerie and
it remained in place for the following 67 years.